Reducing flood risk and reconnecting a creek to its floodplain
Project Case Study
June 2023
Rogers, Arkansas

Project
Blossom Way Stream and Floodplain Restoration
Client
City of Rogers
Location
Rogers, Arkansas
Completion Date
June 2023
*excluding materials
Summary
The City of Rogers initiated this project because of an emergency effort to stabilize the creek and protect the greenway from washing away. The project developed into restoring approximately 825 linear feet of stream channel and reconnecting nearly half a mile of creek to its floodplain. The team used natural channel design methodology to create an appropriately sized channel with a dense riparian buffer and instream structures that deflect erosive forces from the banks and prevent downcutting. Natural Channel Design structures utilized included stacked-rock vanes/j-hooks, cross veins, and constructed riffles. The floodplain restoration was achieved by lowering the adjacent streambanks by 6+ feet to reduce flooding and relieve channel incision. Reduction in bank height greatly reduced the base flood elevation for the surrounding neighborhoods.

The Challenge
The project began as an emergency effort to stabilize an eroding creek threatening nearby infrastructure, including the Razorback Greenway. The channel was incised, with high banks and limited access to its floodplain.

The Approach
The team reshaped the channel using natural channel design methods, installing structures including rock vanes, cross veins, and constructed riffles to manage flow and prevent further erosion.
Adjacent streambanks were lowered by more than six feet to reconnect the creek to its floodplain, reducing pressure on the channel during high flows. A dense riparian buffer was established to support long-term stability.
The Outcome
The creek now has access to its floodplain, reducing localized flooding and stabilizing the channel while protecting surrounding infrastructure and improving habitat.
Project Highlights
- 825 linear feet of stream restored
- ~0.5 miles of floodplain reconnected
- Significant reduction in bank height and flood elevation
- ~39,000 cubic yards of earthwork
Project
Blossom Way Stream and Floodplain Restoration
Equipment Operators
Ryan Rohlfs, TJ Wetherbee, Josh Vail and Eric Chitwood
Construction Cost*
$ {acf_construction_cost}
Stamping Engineer
Karen McCurty
(479) 225-2077
Design & Permitting
Crafton Tull and Associates
*excluding materials
Restoring flow and function through a former lakebed